Duplicate a Baseline

    Only the latest published version of a baseline will be copied to the new baseline.

    Refer to the following steps to create a baseline by copying from an existing baseline:

    1. On the Baselines page, select a baseline with the Retrieved with exception, Unused, or Active status, and click Duplicate.

    2. A suffix _copy is automatically added to the baseline name, and you can update the baseline name.

    3. Ener an option description.

    4. Click Save draft. A new baseline will be created with a draft version.

    Note that only published versions can be applied to tenants. You can publish the draft version when no further edits are needed. For detailed instructions on manage versions, refer to Manage Baseline Versions.